Crane lifting safety and BS 7121

Find out who plans and supervises your lift, what the site team needs to provide and which equipment records you can request.

BS 7121 and crane planning

BS 7121 is the British Standards series on the safe use of cranes. BS 7121-1:2016 gives general recommendations for planning and managing lifting operations. BS 7121-3:2017+A1:2019 covers mobile cranes. On a contract lift, our Appointed Person prepares a plan for the agreed load, crane position and site conditions.

Who is responsible for the lift?

Under CPA crane hire, the hirer arranges competent planning and supervision and directs the lifting operation. Under a contract lift, Ote Lifting takes responsibility for planning, supervising and carrying out the lifting work agreed in the contract. We confirm the scope with you, including who controls access, prepares the crane standing area and provides information about the ground and services.

LOLER and PUWER in the UK

In Great Britain, the Lifting Operations and Lifting Equipment Regulations 1998 (LOLER) require competent planning, suitable supervision and safe execution. The Provision and Use of Work Equipment Regulations 1998 (PUWER) cover matters including equipment suitability, maintenance and training. Northern Ireland has its own 1999 regulations for lifting equipment and work equipment.

Maintenance and thorough examination

Routine maintenance keeps a crane in working order. A thorough examination is a separate assessment of safety-critical parts by a competent person. In Great Britain, unless a competent person’s examination scheme specifies different intervals, lifting accessories and equipment used to lift people require thorough examination every six months. Other lifting equipment generally requires it every 12 months. Exceptional events can also trigger an examination. Tell us which reports your site needs before mobilisation.

Who plans, supervises and signals?

The Appointed Person selects the lifting method and plans the operation. The crane supervisor directs the work to that plan and has the authority to stop it. The operator controls the crane, and the slinger/signaller attaches and directs the load within their agreed role. Before lifting, the crew confirms who gives signals, how the operator receives them and what to do if contact is lost.

Load information, radius and crane configuration

The planner needs the load’s weight, centre of gravity and lifting points. A crane’s headline tonnage does not give its capacity at the landing point. The planned duty depends on the working radius, boom or jib, counterweight and support configuration. The planner checks the applicable manufacturer’s chart and accounts for the hook block and lifting accessories as that chart requires.

Crane standing area and outrigger support

The site team supplies information on the ground or slab, including trenches, cellars, underground services and nearby excavations. The planner identifies the loads the proposed crane set-up will put on the ground. Where engineering input is needed, a competent person assesses the ground or slab and the proposed support. A mat’s surface area alone cannot establish that a crane can stand there safely.

The load route and exclusion zone

Trace the route from pick-up to landing, including the crane’s slewing area. Identify overhead power lines, adjacent structures, public access and other trades. Agree how people will be kept clear, who controls the area and how the signaller will communicate when the operator cannot see the landing point. For work near power lines, involve the line owner in the planning.

When two cranes lift one load

A tandem lift needs a written plan prepared by someone competent in that type of operation. Load sharing, lifting points, movement of the centre of gravity and the sequence need specific assessment. Both crews need a common briefing, a clear line of command and agreed arrangements for stopping the operation.

Weather and changes to the plan

The planner considers the manufacturer’s limits, the load’s exposed area, gusts, visibility and site conditions. A roof panel and a compact machine of similar weight may behave very differently in wind. The plan sets out how conditions are monitored, who can stop work and how changes are assessed before the lift restarts.

Lifting people and planning for rescue

Where people need access at height, the assessment starts with the access method and suitable purpose-designed equipment. Using machinery that was not designed to lift people is exceptional and requires additional precautions. The plan must address supervision, communication and how people can be recovered if equipment fails.

On the day of the lift

The crane supervisor briefs the crew on the agreed plan, communication arrangements and site restrictions. If the load, set-up position or site conditions change, the team stops and refers the change back to the person planning the lift before work resumes.