Contract lifting
With a contract lift, Ote plans, supervises and carries out the lifting work agreed with you. Our Appointed Person prepares the lift plan, risk assessment and method statement (RAMS). We supply the crane, operator and lifting crew.
Deighton Railway ProjectHow a contract lift works
The first step is to agree what needs lifting, where it will land and where our work ends. If your own team will plan and supervise the lift, see CPA crane and operator hire.
Send us the load and site details
Mark the load’s starting and finishing positions on a drawing or photograph. We review the route, any obstructions and the space available for the crane, then agree whether a site visit is needed.
View an AutoCAD Lift PlanAgree the plan, equipment and crew
We select the crane and lifting accessories for the planned lift and arrange the operator, crane supervisor and slinger/signaller. We agree access, the delivery sequence and the handover point with your site team.
Explore the FleetCarry out the lift and hand over the load
Our crane supervisor briefs the team and oversees the lift against the agreed plan. If the load, site or access has changed, the team pauses the work so the change can be assessed before lifting continues. Once the load is in position, we hand it over to the site contact agreed in the plan.
Explore Complex Lifting OperationsLift, transport and position
When a job needs both road transport and a crane, tell us where the load starts and where it needs to finish. We can quote for transport, vehicle escorts where needed and a managed lift at the destination. We’ll agree who handles collection and loading, how delivery fits the lift window and where the load is handed over.
For a combined quote, send both postcodes, the load dimensions and weight, your target dates and photos or drawings of the access at each end.
See how we combined transport, escorts and lifting for gas tanks in Wales.
What to send for a contract lift quote
Start with the postcode, preferred date, load weight and dimensions. Choose the closest match for your job to see what else will help us quote.
Rooftop plant
Send a roof plan with the plant position marked, the building height and a photo from the proposed delivery area. Include the unit dimensions and any delivery slot your installer has booked.
Start a Rooftop Plant EnquiryFactory machinery
Send a layout showing the machine’s current and final positions. Include the doorway dimensions, the handover point and any hours when the production line can stop.
Start a Factory Machinery EnquiryRoadside lift
Mark the proposed crane position and any affected vehicle or pedestrian routes. Tell us about delivery restrictions and any traffic management already arranged.
Start a Roadside Lift EnquiryRailway works
Share the work location, access point, site contact and the working window your project team has agreed. Tell us where the lift affects railway operations and who will arrange access.
Start a Railway Works Enquiry
Industrial Equipment LiftsFrom the delivery vehicle to the final position
For a tank arriving on a trailer, tell us whether the crane will place it directly on its base or hand it over to a team moving it inside. We agree the handover point with your team before selecting the crane and pricing the work.
For rooftop plant, tell us about the roof edge and any screens between the crane and the plant position. For a factory shutdown, tell us which machine must be back in service first.
Factory & Machinery MovesBefore you book a contract lift
These are the details we agree with your site and installation teams before the crane is booked.
What will the quotation cover?
The quote sets out the crane, crew, time on site and work included. For a timed delivery or shutdown, give us the working hours when you enquire. Ask us to identify any transport, traffic management, matting or follow-on machinery move so you can compare quotations on the same basis.
What documents can I ask for before booking?
Send us your procurement or site induction checklist with the enquiry. Tell us if your site needs proof of insurance, operator qualifications or thorough examination reports for the crane and lifting gear. Include any submission deadline so we can confirm what applies to your lift and when we can share it.
Read about lift planning and equipment records or request supplier documents.
What if we only have a drawing?
Send the drawing with the site postcode and your target date. Mark where the load arrives and where it needs to finish. If the weight is provisional, say so. We can discuss the options and identify the manufacturer’s information needed to complete the plan.
Can the work fit a shutdown or a timed delivery?
Tell us when we can first access the site, when the delivery is due and when production must resume. For a changeover, include when the outgoing machine will be ready for collection and who will receive the replacement. We can then agree a sequence and check availability for that window.
Who receives the lift plan, risk assessment and method statement?
Nominate a site contact and tell us if a principal contractor or rail project team needs to review the documents. We agree the issue date and who needs the drawings before mobilisation. Your team can flag changes to access, the load or the programme before the crane travels.
What does your site team provide?
Share the site rules, access restrictions and available information about ground conditions, buried services and overhead obstructions. We agree who will prepare the standing area, manage site access and coordinate deliveries before the crane arrives.
If you have an Appointed Person and lifting team to plan and supervise the work, CPA crane and operator hire is also available. If you already have the crane and need extra people on site, see lifting team hire.
What happens if the lift changes?
A heavier replacement unit, a different crane position or an occupied landing area can change the plan. On an Ote contract lift, the crane supervisor stops the affected work and refers the change to the Appointed Person. The team agrees any revised controls and receives a fresh briefing before the lift resumes.
Lift Team Roles