List the units going up and coming down
Send the manufacturer’s data sheet for the exact unit and confirm how it will arrive on site. A chiller delivered in sections can require a different sequence from one delivered complete. For a replacement, list the old and new equipment separately so we can price the full scope.
Where will the crane collect and land the plant?
Mark the delivery vehicle’s position and the unit’s final position on a roof plan or photograph. Tell us when the old unit will be ready to lift and when the installer can receive its replacement. Include any weekend-only access or areas of the building that must stay open.
Explore Managed Contract LiftingRemoving old rooftop plant
For a changeover, confirm the weight and lifting points of each unit. Ask the building team about the condition of the old unit and who will disconnect it and confirm it is ready to lift. Include screening and parapets on the roof plan so clearance can be assessed.