Plan around the plot sequence
Send the plot layout, delivery schedule and the order in which the frames will go up. Highlight where the delivery vehicles will unload and which plots the crane needs to serve. If you know the weights of the full packs and individual panels, include both and tell us which loads you want lifted as a pack.
Crane and operator hire or a managed contract lift
If your team plans and supervises the lifts, ask for a crane and operator under CPA hire. If you need Ote to plan and supervise the work, ask for a contract lift. Give us the dates each plot will be ready so we can discuss the crane positions and number of visits with your site manager.
See truck-mounted cranes on site
See the Manchester timber frame project.
Böcker Truck-Mounted CranesLifting timber frame panels in sequence
Supply panel sizes as well as weights. A large panel can be sensitive to wind, and the frame contractor’s erection sequence determines when each panel can be received and secured. Agree the handover point and temporary stability arrangements with the erection team.
Weather & Lift Plan Changes