Project facts
- Crane
- Grove GMK4100
- Location
- Tunbridge Wells, Kent
- Load
- 1.2-tonne fibreglass pool shell
- Working radius
- 38 metres
- Landing point
- Prepared garden excavation
Reaching the excavation
The pool shell had to reach the prepared opening in one piece. At the landing point, the horizontal distance from the crane’s centre of rotation to the shell was 38 metres.
Placing the shell
The Grove GMK4100 lifted the shell and lowered it into the garden excavation. The site photograph shows the shell suspended over the opening during the lift.
Planning a similar lift?
Send the pool supplier’s drawing and the weight of the shell as delivered. Show where the delivery lorry can stand and mark the excavation on a plan or a wide photograph. Include the installer’s delivery date and any walls, trees or overhead lines along the route.