Project facts
- Crane
- Jekko 545 spider crane
- Location
- Northampton, Northamptonshire
- Load
- Paper processing machinery
- Set-up
- Compact set-up on the factory floor beside the existing frame
- Work delivered
- Supported installation within the existing steel framework
Install machinery inside an existing frame
The machinery had to go inside an existing frame, with only a small area of factory floor available for the crane.
Reaching into the steel frame
We set up the Jekko 545 beside the steelwork. From there the boom could reach into the frame to support the machinery installation.